What happened

Tepe Enerji Santrali Elektrik Üretim Sanayi ve Ticaret A.Ş. has proposed an additional wind turbine for the Karatepe wind energy facility it operates in Malkara district, Tekirdağ. The plant is located within the Elmalı and Çimendere neighbourhood boundaries.

The planned unit would have 5.56 MWm of mechanical installed capacity and 5.56 MWe of electrical installed capacity. If delivered, the addition would bring the wind plant’s turbine count to seven.

Under the proposal, Karatepe’s total installed capacity would become 45.7739 MWm and 28.36 MWe. The facility has previously been converted into a multi-source electricity generation facility through the addition of a 12.9939 MWm solar power plant.

The reported development is a proposed expansion of an existing generation site. It does not, on the information available, confirm that construction has started or provide a commissioning date.

Why it matters

The plan would increase the wind component of a site already configured to combine wind and solar generation. For asset trackers and power-market participants, the project details distinguish between the proposed turbine’s 5.56 MWm mechanical rating and its 5.56 MWe electrical rating, while also setting out the resulting site-level capacities.

The proposal also indicates how capacity additions can be pursued at an established renewable electricity facility rather than through a separate site development. Readers assessing the asset should update turbine-count and capacity records only as a planned change until the project advances.

What’s next

Tepe Enerji expects construction to require six months. The construction and assembly stages are planned to involve 15 people. Reported project information gives the facility an anticipated economic life of 49 years.

The source does not set out a construction start date, completion date or other project milestones. Stakeholders monitoring the expansion should therefore treat the six-month figure as an expected construction duration rather than a confirmed delivery schedule.

Project details were reported by Enerji Günlüğü.